Efforts continue to diagnose and repair leaks in our water system in preparation for the replacement project.
After determining the majority of the water being lost in division 1 from the concrete tank is occurring on E Cascade Drive, the decision has been made to replace the aging asbestos/concrete 4 inch line. Continuing to band-aid this section of pipe is no longer an option.
The plan during the minimum of 2 week long replacement project when the concrete tank is off is to supply the entire Park from the wooden tank in division 3. While testing the feasibility of this plan another major leak was detected and fixed in division 3. We are still losing water from “Woody” so those leak(s) need to be patched before beginning the replacement project in division 1.
During the period of time everyone is getting their water from Woody everyone must do their utmost to conserve water usage because we will not have the capability to refill the tank. A genuine opportunity to pull together as a community!
A reminder: the entire Park remains under a boil water order until further notice. The board wants everyone to be as safe as possible!
Whatcom Excavation has been doing a fantastic job performing these repairs. The crew actually cares about how the Park is doing, really!
Obviously much coordination and preparation must happen before the projects begin. Owners will be given ample warning to prepare but must realize temporary water outages are still a possibility as leak repairs are underway.
Thank you for your understanding during an extremely distressing time.